Fault Current

The tool takes the transformer, the utility’s fault figure and up to three runs of conductor. It gives the available fault current at the service, the switchboard and the branch circuit, 3-phase and L-N, with every formula shown.

The platform - now showing Fault Current

The drawing

The drawing the Suite made for its own example: a 750 kVA, 5.94 %Z transformer at 480/277 V and three runs of conductor, with the fault current at each point.

Drawing the program wrote: From the utility’s 44,990 A through the transformer to F1 at the service equipment (41,765 A 3-phase), F2 at the switchboard (38,405 A) and F3 at the branch circuit terminal (11,812 A 3-phase, 6,795 A L-N).
From the utility’s 44,990 A through the transformer to F1 at the service equipment (41,765 A 3-phase), F2 at the switchboard (38,405 A) and F3 at the branch circuit terminal (11,812 A 3-phase, 6,795 A L-N).

The report it writes

The report the Suite wrote for this example: every input, each stage’s point-to-point math, the transformer check, then the drawing.

Report page the program wrote: Page 1 of 2
Page 1 of 2
Report page the program wrote: Page 2 of 2
Page 2 of 2

Page 1 lists the inputs and works each fault point, branch first; page 2 is the drawing.

The example, step by step

The Suite’s own example, the values the tool opens with, worked out with Calculate All Stages.

  1. Fault Current in Stinger Pro: The example in, before it is worked out: 750 kVA, 5.94 %Z at 480/277 V, a 44,990 A utility fault, and three stages of 40 ft, 40 ft and 145 ft.

    STEP 1 OF 5The example in, before it is worked out: 750 kVA, 5.94 %Z at 480/277 V, a 44,990 A utility fault, and three stages of 40 ft, 40 ft and 145 ft.

  2. Fault Current in Stinger Pro: Worked out: the red warning says the 44,990 A utility figure is more than this transformer can deliver, and uses it as the conservative figure. Stage 1 gives 41,765 A 3-phase at the main disconnect.

    STEP 2 OF 5Worked out: the red warning says the 44,990 A utility figure is more than this transformer can deliver, and uses it as the conservative figure. Stage 1 gives 41,765 A 3-phase at the main disconnect.

  3. Fault Current in Stinger Pro: Stage 2 gives 38,405 A 3-phase at the switchboard; Stage 3 gives 11,812 A 3-phase and 6,795 A L-N at the branch terminal, each with its f and M shown.

    STEP 3 OF 5Stage 2 gives 38,405 A 3-phase at the switchboard; Stage 3 gives 11,812 A 3-phase and 6,795 A L-N at the branch terminal, each with its f and M shown.

  4. Fault Current in Stinger Pro: The summary and the line for the service disconnect marking: maximum available fault current 41,765 A, with the date of calculation [110.24(A)]. The drawing starts below it.

    STEP 4 OF 5The summary and the line for the service disconnect marking: maximum available fault current 41,765 A, with the date of calculation [110.24(A)]. The drawing starts below it.

  5. Fault Current in Stinger Pro: The drawing: utility, transformer and fault points F1, F2 and F3, with each run’s length and wire and the fault current at each point.

    STEP 5 OF 5The drawing: utility, transformer and fault points F1, F2 and F3, with each run’s length and wire and the fault current at each point.